New Linfield University Portland Campus coming soon signAfter more than a year of diligent planning, renovations began on June 1, 2020 on the new NE Portland Campus, home to Linfield's School of Nursing.

Walsh Construction will begin construction to complete the approved renovations in five campus buildings, with a target end date of mid-November 2020. Chris Adams, director of Portland Campus operations, is the point-of-contact for NE Portland campus access, throughout the period of construction and until the campus move has been completed in early 2021.

It's an exciting time in Linfield’s history! Please contact Allison Horn or Chris Adams with any questions.

Timeline for the new Portland Campus:

  • June 1, 2020: Official campus turnover to Linfield
  • June 1 – Nov. 13, 2020: Renovation period
  • Dec. 21, 2020 – Jan. 29, 2021: Install infrastructure and move-in equipment/furniture
  • Feb. 1 – Feb. 5, 2021: Final preparations
  • Feb. 8, 2021: First day of classes at new Linfield University Portland Campus